The airport is expanding, but when will they actually start building?
One dated promise, comes early
Spain approved its five-year airport plan 15 days early, including investment at Málaga-Costa del Sol. If you fly through Málaga, the terminal expansion still has no verified start date.
On 21 August we wrote: "The next test is dated, the airport decision by 30 September, and if it slips you will read that here too."
Spain's cabinet, the Council of Ministers, approved the plan by agreement on 15 September, ahead of the legal deadline of 30 September. That promise is kept.
DORA is the five-year document that sets what Aena, the state-controlled company running Spain's main airports, may invest and charge across its Spanish network; this one covers 2027-2031.
Approval confirmed from the Transport Ministry and La Moncloa, the prime minister's office, 15 September 2026. The full document was published in Spain's official gazette, the BOE, on 19 September 2026 and checked there on 22 September.
How much money, and what about our tickets?
More than €830 million of investment is planned at Málaga-Costa del Sol airport for 2027-2031. That figure is the government's airport total. The published document splits the regulated part, tied to airport operations: €571.4 million at Málaga over the five years, of which €260.3 million is the terminal expansion.
Across Aena's Spanish network, planned investment is about €13,000 million: €9,991 million regulated, tied to airport operations, and about €3,000 million for commercial activity.
The government says the investment will come from airport-system income, including charges and other revenue, rather than the state budget.
The government's announced average airport charge rises by 0.33% a year across Aena's Spanish network in 2027-2031. Transport minister Óscar Puente described that as about three euro cents per passenger per year, practically a freeze.
Aena had proposed a rise of 3.82% a year and the CNMC, Spain's competition regulator, advised a cut of 0.59% a year, both as an annual component before later adjustments.
The airline associations IATA and ALA asked for a cut of 4.9% a year, excluding inflation. The government's 0.33% matches none of the three.
That average gives us neither a Málaga charge schedule nor a fare. Airlines owe the charge to Aena and may recover it in ticket prices. Any change to your fare remains the airline's decision; we have no measured ticket-price effect.
The part that changed from what we said before
Approval and construction are separate milestones. Our own April issue blurred them.
In our 9 April issue, we said Aena had "committed €1.5 billion" and called Málaga's airport "in the middle of" an expansion. We also wrote that it would "double the current capacity".
Parts held. About €1.5 billion was Aena's estimate for the whole reform-and-expansion project. Aena's proposed design, announced in June 2025, takes the terminal from about 80,000 to about 140,000 square metres, roughly 75% more terminal area. We also said approval was expected in September.
"Committed" overstated a company estimate as approved money. "In the middle of" implied construction; Aena's 2025 announcements established design and procurement. Our primary-source checks to 22 September found no dated construction start.
"Double the current capacity" was wrong because terminal area does not establish passenger capacity. We had no passenger-capacity figure.
The whole-project estimate and the more than €830 million airport total for 2027-2031 have different scopes and may overlap.
On 15 September, Aena reported 3,050,841 passengers at Málaga in August, up 6.6% on August 2025. Those are traffic counts, not unique people.
Our 21 August verdict, "Held, and then some", was too generous: we checked traffic growth and left project delivery untested.
The official version we’ve been given
Most of us learned early to trust the official version over the version from the bar next door. Fair enough, but the habit has a flaw: sometimes the official version is wrong.
The DGT's 23 June release puts the new rule for passing a broken-down or crashed vehicle under "other rules on interurban roads". The regulation has no such limit. If the stopped vehicle is in your lane, you leave 1.5 metres and drop 20 km/h below the limit in town too.
So, which version were you given? It could be a press release, an English translation, a sede — official website FAQ, or a firm's checklist that turned out stricter than the rule.
Hit reply with what it said and where you saw it. We check every one against the text that counts.
The next date worth printing
Article 29 of Spain's Law 18/2014 requires DORA to set completion deadlines for its strategic investments, with monthly penalties for delay. These are completion dates, not start dates. Málaga's terminal expansion is on that list. Table 5.5 of the approved document gives it a completion date of December 2035, a penalty clock that starts in April 2032, and a threshold of €182.2 million to be spent on it before the end of 2031.
The full document reached the BOE on 19 September, issue 232, 118 pages. We have read it. It sets the deadline above and gives no date for the start of works.
Our read: mark each milestone on its own date. The approval gets its mark, 15 September, and the deadline gets its own, December 2035. A completion date is not a building site. If your property case leans on "the airport is doubling", treat that as a plan with a deadline attached. There is nothing to do this week.
Spanish-lite
acuerdo del Consejo de Ministros — Council of Ministers agreement
How Spanish news reports a cabinet decision.
¿Hay fecha de inicio de las obras? — Is there a start date for the works?
For any announced project, from a terminal to the roundabout outside your urbanización.
The bottom line
The date we shared earlier held, with 15 days to spare. Spain approved a five-year plan for airport spending and charges, published it on 19 September, and gave Málaga's bigger terminal a December 2035 completion deadline with no start date for the works. Our read: approval earns its tick; construction earns its own when we can verify that building work has begun.